Cryotherm was awarded the contract to supply and install fire protection to this ten-storey building. The building was to be constructed on a confined site with restricted access.
Also the high density of the fit-out made the distribution of materials extremely difficult. Materials had to be pre-cut and distributed to each work area before internal walls were installed.
Products:
- 10,000m2 of Spiralite fire protection
- 2,000m2 Stoplite
Scope:
- Survey and measurements of ten-storey building
- Supply of all materials
- Installation of fire protection.