passive fire protection lift shaft

Lift Shaft Fire Protection for Landmark Tower Block

Heron Towers is a prestigious, 46-storey office building in central London, where open lift shafts with fully glazed lifts were installed during its construction. Cryotherm was chosen to provide two-hour fire protection, with a decorative finish, to the lift shaft’s steel frame.

Rockliner casings were the ideal choice and the colour Metallic Silver was specified by the architect.

The project included pre and post-sales site surveys, technical advice, fabrication of casings and support framework and the installation, which was undertaken by our approved contractor, Firesafe Installations Ltd.

Products:

  • Rockliner casings, 120-minute Fire Protection to beams and columns
  • Work area within glass elevator shafts, floors 2 to 46 inclusive
  • Columns to be jointed to match full height of the building

Scope:

  • Site measure, propose details and manufacture Rockliner casings
  • Columns to supply in 1375mm lengths with joint details
  • Installation from man hoist, within lift shaft
  • Metallic Silver finish
  • Support framework 1.5mm Galvanised

Find Out More

Contact the expert fabrication and insulation team at Cryotherm to discover how we can design and manufacture your next project.